Osh:Construction of a new terminal at Osh International Airport, covering 25,000 square meters, is on track to be completed by January-February 2027. The terminal is designed to handle around 1,200 passengers per hour, including domestic travelers. This announcement was made by Manasbek Samidinov, head of Airports of Kyrgyzstan OJSC.
According to 24.kg News Agency, construction of the terminal complex began on April 25, 2025. The building spans more than 25,000 square meters, and significant progress has been made, with the main construction work nearing completion. Approximately 90 percent of the flooring is complete, and low-voltage systems are about 70 percent finished, while glazing and facade work are ongoing. Equipment for the terminal has already been delivered.
The new terminal will include a business lounge, a prayer room, dedicated ablution facilities, and children's play areas. Additionally, the project features two boarding gates to facilitate passenger flow.
Meanwhile, the runway reconstruction is proceeding separately and is expected to be completed by the end of 2027. Until that time, the airport will continue its operations, receiving and dispatching aircraft. Samidinov mentioned that the upgraded infrastructure will enhance aircraft handling and expand the airport's operational capacity upon completion.